Members present were Melvin McComber, Brian O'Connor, Chief Building Official; Kathleen Bagley, Director, Recreation and Parks Department. Staff member present was Salvatore Cucia, Assistant Director, Recreation and Parks Department.
Ms. Bagley opened the meeting at 1:30 p.m. She reported that Perry Cornwall and Laura Briggs had contacted her and could not make today's meeting.
No public comments.
A motion was made to approve the minutes by Melvin McComber and seconded by Brian O'Connor. The motion passed unanimously.
Ms. Bagley gave Committee members a summary of the meeting with the architect, Jim Bell. Present at this meeting were Laura Briggs, Nature Center Director; Salvatore Cucia, Assistant Director, Recreation and Parks Department and Kathleen Bagley, Director, Recreation and Parks Department. Ms. Bagley distributed meeting minutes taken by the architect for that meeting. Committee members reviewed the list of items the architect identified in the minutes as they pertain to the design of the Moeller Home. Mel McComber asked if a "walk through" for the Moeller Home could be scheduled once the preliminary design from the architect is available. Ms. Bagley stated that it would not be a problem to have a "walk through" at Moeller Home after the architect's preliminary plans. Ms. Bagley reported that the architect felt the preliminary plans would be available in one or two weeks.
She distributed a letter from the architect identifying the change in engineering firm to be used by Moser, Pilon, Nelson. The letter explained that the previously approved engineering firm of Beemis Associates will be unable to provide consulting engineering services for this project. In lieu of Beemis Associates, Moser, Pilon, Nelson proposed using the firm of L. M. G. Consulting Engineers of Wethersfield. This firm has had a long-standing relationship with Moser, Pilon, Nelson. They anticipate the same level of service as they would have received from Beemis Associates. Committee members had no problem approving the change in engineering firm for the Moeller Home renovation project.
The meeting adjourned at 2:30 p.m.