4/21/2014 - Spring Paving Announced

The Town of Wethersfield will begin the Spring 2014 Pavement Maintenance Program on April 21, 2014. The preparation work is being performed by General Paving & Construction, roadway milling by Costello, and asphalt by TILCON. All work will be supervised by town staff.

The work will include milling or grinding down the pavement surface and complete resurfacing with new asphalt. The milling or grinding is done to replace the road edge along the gutter line in front of driveways at the same elevation which exists today. Preparation work will begin April 21, 2014 Milling will begin May 5, 2014 and paving is anticipated to begin May 12, 2014. The streets will be posted "No Parking" during these weeks.

The following roads are included in this spring program:

STREET FROM TO TYPE OF CONSTRUCTION
Glenwood Dr. Willow St. End Mill & Overlay
Rhodes Cir. Glenwood Dr. End Mill & Overlay
Ridgewood Cir. Willow St. End Mill & Overlay
Clovercrest Rd. Prospect St. Collier Rd. Mill & Overlay
Pebble Rd. Clovercrest Rd. End Mill & Overlay
Peach Hill Rd. Thornbush Rd. Collier Rd. Mill & Overlay
Willow St. Prospect St. House #255 Mill & Overlay
Half Penny Ln. Glenwood Dr. End Mill & Overlay

Residents and commuters are advised that the roads could be closed to all but resident and emergency traffic at times.

Residents and commuters are asked to avoid these areas during these periods, and choose an alternate route, if possible, to avoid traffic delays and inconvenience. Town staff will gladly assist you should you have problems or questions. Please call the Engineering Division at (860) 721-2850 for assistance.